Crossrail Works Programme

The construction of Crossrail is planned to be complete in 2017 with train services introduced over the 12 months following.

As detailed design and development of the scheme progresses there will be increasing certainty over the exact times that works will start and finish at each location where they are to be done. The information below gives the currently assumed timings for main construction works at key locations.

At some locations enabling works (such as the diversion of utilities like gas mains, and demolition of existing buildings) will need to take place before main works. The sites may also be required after main works, for example to support fitting out of stations and tunnels.

This information will be updated as more detail is developed. For current work details please click here

Stations

The following table of station start and completion dates reflects the start of construction (main civil contract works) and when enabling works begin. Where there are separate sites for each station, such as where two ticket halls are being constructed, these are listed below.

Location

Enabling works start

Construction starts

Works complete

Canary Wharf

Dec 2008

May 2009

2016

Tottenham Court Road

Jan 2009

Early 2010

2016

Farringdon

July 2009

Aug 2010

2017

Paddington

Sep 2009

Mid 2010

2016

Whitechapel

Jan 2010

Jan 2011

2016

Woolwich

Early 2010

Early 2011

2016

Bond Street

Dec 2009

Mid 2011

2016

Liverpool Street

Feb 2010

Late 2011

2016

Custom House

Early 2012

Late 2012

2014

Tunnelling Works

The current and 3 month prediction of the progress of the tunnel boring machines will be able to be tracked on the Crossrail website in due course.

The completion dates shown in the following table refer to the completion of the tunnel. Fit out will take place beyond these dates.

Location of Tunnel Drive

TBM Launch

Tunnel Drive Complete

Royal Oak to Farringdon (Drive X)

Oct 2011

March 2013

Limmo to Farringdon (Drive Y)

April 2012

April 2014

Stepney Green to Pudding Mill Lane (Drive Z)

July 2013

March 2014

Limmo to Victoria Dock Portal (Drive G)

July 2014

Nov 2014

Plumstead to North Woolwich (Drive H)

Sept 2012

Oct 2014

On Network Works

Work on stations and tracks on the existing surface railway which will be served by Crossrail will be carried out by Network Rail. These are expected to start in mid 2010. The exact start and duration will vary by location and more detail on the programme will be published when it is available.

Last updated: 22 December 2009