Manufacture of Crossrail’s tunnel boring machines to get underway shortly

By Peter MacLennan

Manufacture of Crossrail’s tunnel boring machines to get underway shortly
  • First tunnel boring machine (TBM) to arrive in London in early 2012

  • Londoners to get chance to name the Crossrail TBMs

  • Crossrail tunnelling to commence in spring 2012 from Royal Oak

  • Tunnelling and Underground Construction Academy to open its doors later this year to train up to 3,500 workers for Crossrail

Crossrail today announced that six of the tunnel boring machines (TBMs) required to deliver the new rail tunnels will be manufactured by Herrenknecht AG, Germany. 

The first two TBMs will arrive in London in early 2012 ahead of being launched from Royal Oak in spring 2012. The TBM manufacturers have been selected by Crossrail’s tunnelling contractors. There are no UK-based tunnel boring machine manufacturers.

Herrenknecht AG will deliver two TBMs to Royal Oak Portal for the western running tunnels in early 2012, two TBMs to Limmo Peninsula for the eastern running tunnels in mid 2012 and a further two machines to Stepney Green later in 2012. 

Londoners will be given the chance to name the tunnel boring machines and will be able to follow their progress as they make their way under the capital via the Crossrail website. Details about how the Crossrail TBMs will be named will be announced during the coming months.

To construct the 21km of twin-bored tunnel required for Crossrail, at least seven tunnel boring machines will be required and will undertake ten individual tunnel drives to construct the 6m diameter rail tunnels. Consideration is currently being given to the need for a further TBM on the short tunnel drive between Limmo Peninsula and Victoria Dock Portal (Drive G). The method of constructing this tunnel section is the subject of ongoing discussions with the tunnelling contractor.

The TBMs required for Crossrail will be up to 120m in length and weigh around 850 tonnes. 

As the Thames Tunnel construction contract has only recently been awarded, the TBM manufacturer for this tunnel drive will be announced later this year.

The six TBMs will be transported to London by boat from the manufacturer’s factory in Schwanau, Germany. The specific points of arrival in the UK are yet to be agreed between the manufacturer and the tunnelling contractors. Before they depart for the UK they will be fully assembled and tested before being dismantled into sections ready for transport.

The cutter heads for the tunnel boring machines will arrive in sections and will be transported to the tunnel launch sites and assembled.

There will be two different types of TBM to reflect the differing ground conditions along the Crossrail route. All of the tunnel boring machines, except for the TBM used to construct the Thames Tunnel, will be Earth Pressure Balance Machines, which will be used for the main running tunnels between Royal Oak, Pudding Mill Lane and Victoria Dock Portal. These will pass through ground which is predominantly London clay, sand and gravels. The Thames Tunnel, which is predominantly constructed through chalk, will use a Slurry TBM.

The Mayor of London, Boris Johnson said: “There is nothing boring about the leviathan machines that will soon be burrowing their way through the earth way below our streets. These monsters of the deep will create the tunnels that will make it easier for millions of people to whizz east to west across our city.”

Rail Minister Theresa Villiers said: “This is an exciting step forward for the Crossrail project, which will revolutionise rail travel in the capital, create thousands of new jobs and deliver real benefits to the London and UK economies.”

Rob Holden, Crossrail Chief Executive said:  “In less than a year, the first tunnel boring machines will have arrived and begun their journey from Royal Oak to Farringdon. I’m delighted that Londoners will be given the chance to name the machines that will build the major new rail tunnels under London. Even though the start of tunnelling is still about nine months away, work has been ongoing since early 2010 to construct the tunnel portal at Royal Oak from where the first TBM will launch.”

The TBMs will run nearly 24 hours a day, 7 days a week, 365 days a year. There will be scheduled breaks to allow maintenance on the TBMs to take place and tunnelling activity will stop for certain public holidays including Christmas Day.

Each TBM will be operated by a ‘tunnel gang’ comprising of around twenty people - twelve people on the TBM itself and eight people from working from the rear of the machine to above ground.

As the TBMs advance forward, precast concrete segments will be built in rings behind the TBMs. Crossrail today also confirmed that the concrete segments for the western running tunnels between Royal Oak and Farringdon will be manufactured at Old Oak Common and transported to the TBM by rail. Crossrail is currently finalising arrangements with the tunnelling contractors for location of the other concrete segment manufacturing sites.

Such is the scale of Crossrail that up to 14,000 people will be employed at the peak of construction between 2013 and 2015 giving Londoners the chance to build and benefit from Crossrail. Currently 3,000 people are employed on the Crossrail project. 

Construction continues to advance on the new Tunnelling and Underground Construction Academy in east London which has recently ‘topped out’ which means that the structure is watertight. The Academy will offer training to at least 3,500 people in underground construction alone over the life of the project. It will provide training on the key skills required to work in tunnel excavation and underground construction and aims to address the shortage of people with the necessary skills to work on Crossrail. The Academy will be fully open by September 2011.

NOTE: Many features on the website require Javascript. You can enable it via your browser's preference settings.

Ends

For further information contact Crossrail Press Office on 0203 2299 552 or email [email protected]

Notes to Editors:

Herrenknecht AG is based in Schwanau, Germany. Schwanau is located close to the German / French border, about 100km south of Strasbourg.

In spring 2012, the first two tunnel boring machines will start on their journey from Royal Oak towards Farringdon. This will be followed later in 2012 by the launch of two further tunnel boring machines in Docklands that will head towards Farringdon under central London. The Thames Tunnel drives will commence at the end of 2012, followed by further shorter tunnel drives under the Royal Docks and east London.

The five tunnels to be constructed are:

  • Royal Oak to Farringdon west (Drive X) - length of drive approximately 6.1 km
  • Limmo Peninsula in the Royal Docks to Farringdon east (Drive Y) - length of drive approximately 8.3 km
  • Stepney Green to Pudding Mill Lane (Drive Z) - length of drive approximately 2.7 km
  • Limmo Peninsula in the Royal Docks to Victoria Dock Portal (Drive G) - length of drive approximately 0.9 km
  • Plumstead to North Woolwich (Drive H) - length of drive approximately 2.6 km

All of this adds up to 42km of bored tunnels located below the busy streets of London.

Crossrail’s tunnel boring machines will be employed as follows:

  • Royal Oak to Farringdon (Drive X) – 2 x earth pressure balanced TBMs
  • Limmo to Farringdon (Drive Y) – 2 x earth pressure balanced TBMs
  • Stepney Green to Pudding Mill Lane (Drive Z) – 2 x earth pressure balanced TBMs
  • Limmo to Victoria Dock Portal (Drive G) – 1 or 2 x earth pressure balanced TBMs,
  • Plumstead to North Woolwich (Drive H) – 1 x slurry TBM (with two separate cutter heads for the eastbound and westbound drives)

Five tunnel portals will be constructed as part of Crossrail at Royal Oak, Pudding Mill Lane, North Woolwich, Victoria Dock and Plumstead.

The main Western and Eastern running tunnels will have tunnel portals at Royal Oak, Pudding Mill Lane and Victoria Dock. The tunnel boring machines (TBMs) will commence their eastbound journey under London from Royal Oak and westbound from the Royal Docks. 

To deliver Crossrail services to Abbey Wood, a tunnel will be constructed between North Woolwich and Plumstead – the Thames Tunnel. Tunnel portals will be constructed at either end in advance of the main tunnelling works.

Construction of the first tunnel portal at Royal Oak got underway in January 2010 and is due to complete in early 2012. 

Tunnel construction schedule:

Location of Tunnel Drive

TBM Launch

Tunnel Drive Complete

Royal Oak to Farringdon (Drive X)

Second Quarter 2012

Third Quarter 2013

Limmo Peninsula to Farringdon (Drive Y)

Third Quarter 2012

Third Quarter 2014

Stepney Green to Pudding Mill Lane (Drive Z)

Fourth Quarter 2013

Third Quarter 2014

Limmo Peninsula to Victoria Dock Portal (Drive G)

Second Quarter 2014

Third Quarter 2014

Plumstead to North Woolwich (Drive H)

Fourth Quarter 2012

Second Quarter 2014