- Home
- …
- Our Plan to Complete the Elizabeth Line
- Signalling and Testing
Signalling and Testing on the Elizabeth line
Our plan to complete the outstanding works and bring Elizabeth line into passenger service continues to make progress but we are in the most challenging phase of the project, with software development and systems integration to be completed.
The Elizabeth line will increase central London's rail capacity by ten per cent and will carry more than 200 million passengers per year. It also represents the first-time national rail lines to the east and west of London have been connected through an underground metro system.
The Elizabeth line consists of three sections – the new build central section, and the east and west surface sections.
Download our Elizabeth line Signalling Fact Sheet
SIGNALLING
Technical Director Colin Brown explains how the Elizabeth line will operate under the three different signalling systems across the route.
Gallery - Crossrail Integration Facility
-
Siemens - Chippenham Site_325041 -
Siemens - Chippenham Site_325043 -
Siemens - Chippenham Site_325040 -
Siemens - Chippenham Site_325039 -
Siemens - Chippenham Site_325038 -
Siemens - Chippenham Site_325036 -
Siemens - Chippenham Site_325035 -
Siemens - Chippenham Site_325034 -
Siemens - Chippenham Site_325044 -
Siemens - Chippenham Site_325042 -
Siemens - Chippenham Site_325045
SYSTEMS INTEGRATION AND TESTING
Testing Manager Daniel O'Connell explains how Crossrail must complete testing of the technical railway systems, known as Dynamic Testing, before intensive trials to simulate the full railway service, known as Trial Running.
Gallery - Train testing on the Elizabeth line
-
Paddington Routeway_337847 -
Bond Street Routeway_337840 -
Bond Street Routeway_337839 -
Bond Street Routeway_337838 -
Bond Street Routeway_337838 -
Bond Street Routeway_337837 -
Central section tunnels and routeway during Dynamic Testing _336218 -
Central section tunnels and routeway during Dynamic Testing_336213 -
Farringdon Station_333598 -
Central section tunnels and routeway during Dynamic Testing_336214 -
Route Control Centre _Romford_Operations Room_327856 -
Central section tunnels and routeway during Dynamic Testing_336211 -
Route Control Centre _Romford_Simulation Room_327926 -
Central section tunnels and routeway during Dynamic Testing_336216 -
Dynamic Testing _August 2019_325743 -
Central section tunnels and routeway during Dynamic Testing_336209 -
Inside cabin view from multi-train Dynamic Testing_323140 -
Inside cabin view from Dynamic Testing_321736 -
Dynamic testing_Platform Screen Doors at Liverpool Street Station_325345 -
Stepney Green Junction_325079 -
Central section tunnels and routeway during Dynamic Testing_336217 -
Stepney Green Junction_325082 -
Stepney Green Junction_325084 -
Stepney Green Junction_325087 -
Elizabeth line test train exiting Victoria Dock Portal_303064